Friday, April 29, 2016

ACCOMPLISHMENTS OF THE WEEK
APRIL 29
  • Got 90 percent complete for the autonomous
  • Got the pars for he next arm challenge
  • Started putting together the new arm
  • Made adjustments 

Monday, April 25, 2016

GOALS OF THE WEEK
APRIL 25

  • Complete the programming for autonomous
  • Complete the autonomous challenge
  • Start building the arm for the next challenge
  • Take the old arm off the robot

Friday, April 22, 2016

ACCOMPLISHMENTS OF THE WEEK
APRIL 22

This was a short week, only a couple days so we accomplished some but not all goals
  • We signed up for GMetrix
  • Started the autonomous
  • Built the tetrahedron

Monday, April 18, 2016

GOALS OF THE WEEK 
APRIL 18

  • Build the arm on the robot in solid works
  • Build the tetrahedron
  • Practice putting in on the pipes
  • Start the autonomous
  • Practice with the autonomous

Friday, April 1, 2016

ACCOMPLISHMENTS OF THE WEEK
APRIL 1ST
  • We did three laps with our robot
  • Made adjustments in the autonomous
  • Started to work for the next challenge
  • Built the arm